Nuevitas, Aug 4.- During the months of July and August, the group at the 10 de Octubre thermoelectric plant, in this Camagüey municipality, exceeded the energy generation plan.
Jorge Luis Maceira Esteva, general director of the plant, reported that in the eighth month of the year, of 92,000 megawatts (mw) they contributed 95,000 mw to the National System, given that they exceeded the average commitment of 150 mw per hour (mw/h) during the summer stage.
These days, 10 de Octubre keeps units 5 and 6 in operation, with 70 and 100 mw/h of generation, respectively, an example of the commitment of the men and women who from there adopt alternatives to challenge the consequences of the economic and commercial blockade. and financial from the United States to the island.
Likewise, during the period they repaired breakdowns, changed an oil cooler in a pump, maintained automatic schemes and small leaks in the boiler, according to publications on the profile on the social network Facebook.
A positive aspect in Nuevitas was the maintenance of the pumping stations and water conduits to the industry, which guarantees a stable input of more than 300 cubic meters per hour to the thermoelectric plant, added the manager. (Text: Arianna Suárez Torres/ Radio Nuevitas) (Photo: Radio Nuevitas)